METHOD FOR CONSTRUCTING STEEL SHEET PILE COFFERDAM ON DEEP SAND GRAVEL OVERBURDEN LAYER

在深砂砾层上建造钢板桩围堰的方法
著录项
摘要
构建钢板桩围堰的方法包括以下步骤:\n\n步骤S1:确定钢板桩围堰的施工面积;\n步骤S2:堆置钢套管,并将导向架支架焊接在钢套管上,导向架支架与导向架和限位夹板相连;\n步骤S3:依靠导向架堆置钢板桩;\n步骤S4:在钢板桩围堰底部浇筑封底混凝土;\n步骤S5:在钢板桩围堰内设置檩条和内部支撑;\n步骤S6:在钢板桩围堰底部进行二次封底;\n步骤S7:通过泵抽水并在封底混凝土上浇筑形成承载平台;\n步骤S8:在形成承载平台后拆除钢板桩围堰。
【原文】A method for constructing a steel sheet pile cofferdam is provided, including: step S1, determining a construction area of the steel sheet pile cofferdam; step S2, piling steel casings, and welding guide frame brackets to the steel casings, the guide frame brackets are connected with a guide frame and limiting clamp plates; step S3, piling steel sheet piles by relying on the guide frame; step S4, pouring subsealing concrete at a bottom of the steel sheet pile cofferdam; step S5, arranging purlins and internal supports within the steel sheet pile cofferdam; step S6, perform a secondary subsealing at the bottom of the steel sheet pile cofferdam; step S7, pumping water within the steel sheet pile cofferdam through a pump and pouring to form a bearing platform on the subsealing concrete; step S8, removing the steel sheet pile cofferdam after the bearing platform is formed.

网页搜索
学术搜索